Foundation & Structure
Foundation & Structure includes materials for the basic house structure including foundation, floors, walls, roofing, and plastering.
Bricks, Cement, Sand, & Crush
15.26 Lakh
ITEM | RATE | QUANTITY | COST |
---|---|---|---|
Bricks + Rorhi | 24/Unit | 33757 | 810,168 |
Cement | 1150/Bag | 363 | 417,450 |
Sand | 76/Cft. | 1815 | 137,940 |
Crush | 155/Cft. | 1033 | 160,115 |
Roof Insulation, Termite & Water Proofing
33.56 Thousand
ITEM | RATE | QUANTITY | COST |
---|---|---|---|
Roof Insulation | 231/Sft. | 87 | 20,097 |
Termite Proofing | 1500/Liter | 3 | 4,500 |
Water Proofing | 103/Sft. | 87 | 8,961 |
Excavation & Steel Reinforcement
5.98 Lakh
ITEM | RATE | QUANTITY | COST |
---|---|---|---|
Excavation & Backfill + Ghassu | 20/Cft. | 2217 | 44,340 |
Steel Reinforcement | 277000/Tonne | 2 | 554,000 |
Labor Cost
4.92 Lakh
Plumbing Works
Plumbing works include underground piping and drainage systems materials.
4.92 Lakh
Cold and Hot Water Supply
27.46 Thousand
Insulation Armaflex
18.56 Thousand
Drainage System Piping
59.78 Thousand
Gas Piping
36.46 Thousand
Pumps and Drains
2.67 Lakh
AC Drainage System
8.53 Thousand
UPVC Pipeline for Sewerage System
20.13 Thousand
Labor Cost
53.46 Thousand
Electrical Works
Electrical works include underground wiring and all electrical items.
7.07 Lakh
Grey Structure 99.35 Thousand
Finishing 6.08 Lakh
Switches and Back Boxes
1.76 Lakh
Conduits & Accessories
30.54 Thousand
Wires & Cables
2.41 Lakh
Lights, Fans and Chandeliers
2.03 Lakh
Labor Cost
55.89 Thousand
Wood, Metal and Tile Works
Wood, Metal & Tile Works include cabinets, wardrobes, flooring, and all aluminum and iron works.
21.45 Lakh
Paint and Ceiling Works
3.24 Lakh
Tile Work
5.86 Lakh
Wooden Doors
4.69 Lakh
Windows
1.65 Lakh
Metal Works
1.81 Lakh
Wardrobes & Cabinets
4.20 Lakh
Fittings & Fixtures
Fittings & Fixtures include kitchen and bath accessories.
4.48 Lakh
Kitchen
56.98 Thousand
Bathroom
3.56 Lakh
Geyser & Manhole
34.76 Thousand