Breakdown of Overall Construction Cost By Percentage (PKR)

Foundation & Structure

Foundation & Structure includes materials for the basic house structure including foundation, floors, walls, roofing, and plastering.

 

Bricks, Cement, Sand, & Crush

15.26 Lakh

ITEM RATE QUANTITY COST
Bricks + Rorhi 24/Unit 33757 810,168
Cement 1150/Bag 363 417,450
Sand 76/Cft. 1815 137,940
Crush 155/Cft. 1033 160,115

 

Roof Insulation, Termite & Water Proofing

33.56 Thousand

ITEM RATE QUANTITY COST
Roof Insulation 231/Sft. 87 20,097
Termite Proofing 1500/Liter 3 4,500
Water Proofing 103/Sft. 87 8,961

 

Excavation & Steel Reinforcement

5.98 Lakh

ITEM RATE QUANTITY COST
Excavation & Backfill + Ghassu 20/Cft. 2217 44,340
Steel Reinforcement 277000/Tonne 2 554,000

Plumbing Works

Plumbing works include underground piping and drainage systems materials.

4.92 Lakh

Electrical Works

Electrical works include underground wiring and all electrical items.

7.07 Lakh

Grey Structure 99.35 Thousand
Finishing 6.08 Lakh

Wood, Metal and Tile Works

Wood, Metal & Tile Works include cabinets, wardrobes, flooring, and all aluminum and iron works.

21.45 Lakh

Fittings & Fixtures

Fittings & Fixtures include kitchen and bath accessories.

4.48 Lakh