5 Marla House Plumbing Works Cost in Lahore

Plumbing Works

Plumbing works include underground piping and drainage systems materials.  6.36 Lakh

Cold and Hot Water Supply

45.63 Thousand

ITEM RATE QUANTITY COST
25 mm o/d Pipe 94/Rft. 203 19,082
32 mm o/d Pipe 159/Rft. 81 12,879
40 mm o/d Pipe 237/Rft. 20 4,740
50 mm o/d Pipe 357/Rft. 25 8,925

Insulation Armaflex

31.35 Thousand

ITEM RATE QUANTITY COST
32 mm o/d 422/Rft. 41 17,302
50 mm o/d 562/Rft. 25 14,050

Drainage System Piping

99.40 Thousand

ITEM RATE QUANTITY COST
2″ Dia. Pipe 241/Rft. 81 19,521
3″ Dia. Pipe 325/Rft. 81 26,325
4″ Dia. Pipe 439/Rft. 122 53,558

Gas Piping

61.30 Thousand

ITEM RATE QUANTITY COST
GI Welded Pipeline 3/4” i/d 387/Rft. 152 58,824
Gas Cock 3/4″ i/d 1240/Unit 2 2,480

Pumps and Drains

2.61 Lakh

ITEM RATE QUANTITY COST
Booster Pump 0.75 HP 124000/Unit 1 124,000
Submersible Water Transfer Pump 1 HP 125557/Unit 1 125,557
Floor Drains 1590/Unit 7 11,130

AC Drainage System

14.25 Thousand

ITEM RATE QUANTITY COST
1″ dia Class “E” 104/Rft. 137 14,248

UPVC Pipeline for Sewerage System

34.22 Thousand

ITEM RATE QUANTITY COST
6″ dia Class “B” 671/Rft. 51 34,221